Challenger and the O-Rings
On July 31, 1985, Morton Thiokol engineer Roger Boisjoly sent his company's engineering vice president a memo about the rubber O-rings that sealed the joints of the shuttle's solid rocket boosters. After a recent flight in which a primary O-ring had failed to seal, he warned that a joint failure could cost lives, and he urged a dedicated team to fix the problem. The team was set up, but its own members complained it was constantly delayed.
Cold made the seals worse. A January 1985 launch at an O-ring temperature of 53°F, the coldest to that point, had shown erosion in both boosters. On the evening of January 27, 1986, with a freezing night forecast in Florida, Thiokol engineers told NASA on a teleconference that they should not launch below 53°F. NASA managers at Marshall Space Flight Center pushed back. During an offline caucus, a senior Thiokol executive told the engineering vice president to take off his engineering hat and put on his management hat. Thiokol then recommended launch.
Challenger lifted off the next morning in 36°F air and broke apart 73 seconds later, killing all seven crew members. The Rogers Commission found the decision to launch was flawed and that Thiokol management had reversed its engineers to accommodate a major customer.
Verdict: ConfirmedThe Rogers Commission documented both the 1985 memo and the night-before warning against a cold-weather launch.